Supervision of construction and installation of Unit 15 of Dung Quat oil refinery - Residue Fluid Catalytic Cracking Unit (RFCC). This is the most important workshop in the plant, transforming high-temperature petroleum segments (or having large molecules) (from CDU workshops) into high-quality gasoline.
Construction and installation of power management and control system EMCS with power control function 22/6/ 0.4 kV for the whole plant.
Commissioning of DCS system of RFCC workshop, EMCS system, automatic valve system, tank monitoring system, air compressor system etc.
Maintenance Field Instruments such as control valves, transmitters, flame detector, tank gauging system, etc.